1,090,000’ trenching, boring, and collector system installation.
Terminated and tested MV cables in 200 GE WTG’s, junction boxes, and MV splices.
Fiber optic cable jetting, terminations and testing in WTG’s and substation.
400,000’ trenching, boring, and collector system installation.
Terminated and tested MV cables in 82 GE WTG’s, junction boxes, and MV splices.
Fiber optic cable jetting, terminations and testing in WTG’s and substation.
200,000’ trenching, boring, and collector system installation.
Terminated and tested MV cables in 115 Siemens Gamesa WTG’s, junction boxes, and MV splices.
Fiber optic cable jetting, terminations and testing in WTG’s and substation.
100,000’ trenching, boring, and collector system installation.
Terminated and tested MV cables in 38 Siemens Gamesa WTG’s, junction boxes, and MV splices.
Fiber optic cable jetting, terminations and testing in WTG’s and substation.
330,000’ trenching, boring, and collector system installation.
Terminated and tested MV cables in 74 GE WTG’s, junction boxes, and MV splices.
Fiber optic cable jetting, terminations and testing in WTG’s and substation.
Hooker Brothers Construction 2019 Wind and Solar Farms Projects:
Hooker Brothers Construction 2018 Wind and Solar Farms Projects:
Hooker Brothers Construction 2017 Wind and Solar Farms Projects: